The days the installers spend in your garden are the short part of a pool fence project. Measuring, made-to-measure parts, groundwork and permits take longer than the fitting itself. Here is what to expect for each type of fence, and for a retractable fence in particular.
- 1Site preparation
A perimeter channel with power and drainage points, prepared to our drawings.
- 2System installation
Modular units are placed, anchored to the concrete and levelled.
- 3Connection and setup
Drainage and control cables are connected and the system is commissioned.
- 4Testing and handover
A full operating test, a briefing for you and the documentation.
Typical times by fence type
These are typical figures for a standard backyard pool. Your supplier's schedule is the one that counts.
| Fence type | Time on site | What happens first |
|---|---|---|
| Removable mesh | Usually half a day to one day | A measuring visit. Poles and mesh are stock items, so lead times are short |
| Aluminium or steel panels | One to three days | Posts are often set in concrete, which has to cure before gates are hung |
| Frameless glass | Two to five days | Panes are made to measure, so allow several weeks before the fitting date |
| Automatic safety cover | One to three days | Made to measure, and the housing is usually built with the pool |
| Retractable fence (Smart Fence) | About one working day for up to eight units | The channel, the drain and the cables are prepared before the units arrive |
So a mesh fence around a standard pool is normally a one-day job. A retractable fence is also about a day on site for a typical pool. The difference is in what has to be ready beforehand.
Why the times differ
Removable mesh. The crew marks the line, drills a sleeve into the deck about every metre, sets the poles, tensions the mesh section by section and hangs the self-closing gate. On a concrete or stone deck around a standard backyard pool that is half a day to a day. It takes longer where there is no solid deck to drill, because each pole then needs its own footing.
Aluminium or steel panels. The panels go up fast. The posts are the slow part: set in concrete, they need a day or more to cure before a gate can hang from them. Slopes add time, because the panels have to step down the ground.
Frameless glass. Toughened glass cannot be cut once it is made, so every pane is produced to the final measurements. That is the wait of several weeks. On site the spigots or the channel are fixed first, then the panes are set, lined up and grouted, and the gate hardware is adjusted last.
An automatic cover. The mechanism and its housing are part of the pool's construction. On an existing pool the tracks and the housing have to be fitted to what is there, which is slower.
A retractable fence. The fitting is quick because the hard work is in the ground before the units arrive.
A retractable fence, stage by stage
Every Smart Fence project follows the same order.
- Site survey. We, or your local distributor, look at the pool, the paving, the power supply and the drainage.
- Technical drawings. You receive the layout of the perimeter and the preparation drawings for your contractor.
- Groundwork. Your contractor prepares a concrete channel 30 to 35 cm below the paving line and at least 70 cm wide. The plumber provides a drain point with a 50 mm pipe to the drain or a soakaway. The electrician provides a power point for the controller, a 9 × 1.5 mm² cable from the controller to each unit and a two-core cable to the gate unit. How long this takes depends on your contractor and on the site, and fresh concrete needs time to cure.
- Installation. The units are set along the pool, anchored to the concrete on four feet and levelled to the finished floor. A typical pool, up to eight units, takes about one working day.
- Connection and commissioning. Our team wires each unit box and starts the system.
- Finishing. The paving or decking is brought up to the handrail on both sides, and a tile or decking inlay is fitted if you chose one.
- Testing and handover. A full function test, a walkthrough with you, and the documentation.
Longer fence lines take proportionally longer: sixteen units is roughly two days of installation.
- 30 to 35 cmConcrete base, below the paving
- 70 cmChannel width, at least
- Up to 4 mUnit length, made to measure
- 1 dayTypical installation, up to 8 units
Existing pool or new build?
On a new build the channel, drain and cable routes are cast with the terrace. The fence adds almost nothing to the programme, because the trades are already on site.
On an existing pool the channel is cut at paving level. The pool itself is not touched, and most gardens keep their design intact, but cutting, casting and making the paving good add days that a new build does not have. The installation guide shows the channel in section.
The whole project, from first call to handover
Count the calendar, not the installation day.
| Stage | Who does it | What sets its length |
|---|---|---|
| First layout and enquiry | You | A few minutes in the configurator |
| Site survey and drawings | Us or your local distributor | Diaries, and how soon the site can be measured |
| Permit, where one is needed | Your building authority | Its own timetable: ask before anything else |
| Production | The factory | Units are made to measure; ask for the current production time when you order |
| Groundwork | Your contractor | The site, the weather and the curing of the concrete |
| Installation and connection | Our team | About one working day for up to eight units |
| Finishing the paving | Your contractor | The stone or decking you chose |
| Testing and handover | Our team, with you | A visit of a few hours |
Three of these can run side by side: the permit, the production and the groundwork. Installation day can only be booked when all three are finished, so the slowest of them decides your date.
Permits and inspections
In many places a pool barrier is part of a building approval, or has to be inspected before the pool may be filled or used. Where that applies, three things follow.
- Ask first. Find out what your authority accepts and what it wants to see before you choose a fence. A retractable barrier is accepted in some places and not in others. The rules by country are a starting point, and the written answer of your own authority is what counts.
- Book the inspection early. Inspectors have diaries too, and a pool that waits three weeks for a visit is three weeks without swimming.
- Have the gate working. An inspection usually tests that the barrier is complete and that the gate closes and latches by itself. A fence that is finished except for the gate is not finished.
Season and weather
- Spring is the queue. Everybody wants the pool ready for summer, so surveyors, contractors and installers are booked up from early spring. Projects ordered in autumn or winter move faster.
- Cold and heat. Concrete cures slowly in cold weather and needs care in great heat. Either way, the groundwork takes the time it takes.
- Rain. Cutting, casting and paving stop when it rains.
- The quiet months. The best time for groundwork is when the pool is closed anyway. The days with an open channel then fall when nobody is swimming.
What slows a project down
- Permits and inspections. Where a barrier is part of a building approval, the paperwork sets the pace.
- Made-to-measure parts. Glass panes, custom covers and cut units are produced after the final measurements.
- Weather and curing. Concrete cannot be rushed, and rain stops groundwork.
- Finished paving. Cutting through stone that is already laid is slower than casting a channel in a new slab.
- Long routes. A controller far from the fence, or a drain point at the other end of the garden, means more trenching.
- Late decisions. Choosing the handrail finish after the paving has been ordered is the most common cause of delay.
- Trades waiting for each other. The plumber and the electrician need to finish before installation day, not on it.
How to keep it short
- Decide on the barrier while the pool or the terrace is still being designed.
- Give the preparation drawings to your contractor as soon as you have them.
- Choose the handrail finish before the paving is ordered, so the same tile can be used.
- Have the drain and the cables finished and checked before the units arrive.
- Keep access clear on installation day.
Questions to ask about timing
- When can the site be surveyed, and when will I have the drawings?
- How long is production at the moment, counted from the approved drawings?
- What exactly must my contractor finish before installation day?
- Who checks the groundwork, and when?
- How many days will your team be on site, and what could add a day?
- Who arranges the inspection, if one is needed?
- What happens to my date if it rains?
Staying safe during the work
A garden with an open channel and no finished barrier has less protection than usual, not more. Agree temporary fencing with your contractor for the days between the start of the groundwork and the handover, and keep children away from the site.
Short answers
How long does it take to install a mesh pool fence? Usually half a day to one day for a standard backyard pool with a solid deck.
How long does a glass pool fence take? Two to five days on site, after several weeks while the panes are made.
How long does a retractable pool fence take? About one working day for up to eight units, once the channel, the drain and the cables are ready. The groundwork before it takes longer than the fitting.
Can a pool fence be installed in one day? A mesh fence, yes. A retractable fence, yes for a typical pool, when the ground has been prepared. Glass and panel fences usually need more than one visit.
Can we use the pool during the work? Not while a channel is open or a barrier is unfinished. Plan temporary fencing for those days.
Planning your own schedule
Send us your layout from the configurator. It shows the number of units and the site work your pool needs, and the timetable is fixed after the site survey. A fence is one layer of protection, and never a replacement for an adult watching the water.